Open raceNo supplier dominates: 18 different companies have won the last 20 comparable contracts from this buyer over 5 years. This is a genuinely open race.
- Expected final price vs the published estimate
- -4.1%
Based on 20 comparable awards by this buyer in this sector over 5 years. Every verdict is recorded before the outcome and graded against the award notice. How we score ourselves.
Summary
Machine-generated summaryThe Natural Resources Institute Finland (Luke) is procuring a new research greenhouse for its Piikkiö research infrastructure area, delivered as a design and build contract (KVR) in accordance with the tender documents. The contract covers the design of the project starting from the project plan readiness level, demolition works on three existing greenhouses, and the construction of the new research greenhouse to a fully finished state. The works are located at Luke's Piikkiö research infrastructure site in Finland. The scope thus combines design, demolition and complete construction under a single main contractor's responsibility.
Description
Bid or no-bid?
Six questions before you commit a team. Under each one, what the register holds on it. The answers are yours.
Can I bid?
- Open procedure: any interested supplier may submit a bid.
- The notice is written in Finnish.
- Tender documents: tarjouspalvelu.fi
- Certificates from another EU country? Check the equivalents on eCertis
Official source
Source: HILMA - hankintailmoitukset.fi (Hansel Oy)
Always verify details on the official notice.
Report an error in this notice
Last verified against HILMA - hankintailmoitukset.fi (Hansel Oy) 4 hours ago
The official portal may ask for a free registration before downloading.
What this buyer has paid before
Based on 20 comparable contracts this buyer awarded in this sector over the last 4 years.
- Median award
- €1.3M
- Middle half of past awards
- €332,000 to €14.3M
HILMA - hankintailmoitukset.fi (Hansel Oy) publishes no value for this notice, so it has no mark on the scale. The official documents may state one.
Most recent awards
- Construction works - PKI202009 Restaurant and health station €6,565,026
- Construction work - MIGRI Helsinki detention unit, new building, main contract €35,000,000
- Suomi - Rakennustyöt - A202683 Asuntolarakennusten peruskorjaus €4,953,281
- Suomi - Rakennustyöt - A202501 Tähtelä, majoitusrakennus €1,098,000
- Suomi - Rakennustyöt - A202749/A202996 Helsingin ja Kylmäkosken vankiloiden uudet selliosastot €20,957,040
Award values as published by the official sources. Use them as a guide, not a rule: scope, lots and duration differ between contracts.
The buyer
Full buyer profileSenaatti-kiinteistöt
- notices in the register
- 183
- awards
- 43
- awarded in total
- €372.9M
Who wins its contracts
Many suppliers- different companies won its awards
- 30
- of the awards went to the three most frequent winners
- 19%
- of its calls state an estimated value
- 26%
Based on 36 awards with a named winner over the last 3 years. Counted by award, not by value, because lot and framework amounts are not comparable. Concentrated means the three most frequent winners took 65% or more of the awards; many suppliers, under 35% with at least ten different winners.
Competition
- tenders per lot on average (open and restricted procedures)
- 4.0
- of those lots received a single tender
- 3%
- of the awards went to companies based in another country
- 0%
As the official award notices state them, over the last 3 years. Tenders per lot count open and restricted procedures only: in a negotiated procedure or a direct award a single tender is the procedure itself. The country is the one the notice gives for the winner.
One dot per award, on the day it was signed, sized by its value. A ring is an award with no published value.
Who usually wins this buyer's contracts in this sector
| Company | Wins | Total awarded | Last win |
|---|---|---|---|
| Lujatalo Oy | 2 | €87.2M | Jun 2026 |
| JP Yhtiöt Oy | 2 | €607,000 | Nov 2025 |
| Consti Korjausrakentaminen Oy | 1 | €195.0M | Nov 2025 |
| Adapteo Finland Oy | 1 | €21.0M | Jan 2026 |
| Peab Oy, Pohjanmaat | 1 | €14.6M | May 2026 |
Based on 20 awards with a linked company profile over the last 5 years.
26 open tenders right now
- Opera House basic renovation 2026-2028: window renovation and replacement contract 1 day left
- Opera House basic renovation 2026-2028 - Glass wall and roof window contract 6 days left
- Repair and maintenance of refrigeration equipment - Refrigeration equipment maintenance and repairs for Senate Properties in Southern and Eastern Finland 11 days left
Market context
HILMA - hankintailmoitukset.fi (Hansel Oy) publishes no value for this notice, so it cannot be placed among the open notices of its sector. The official documents may state one.
- open now in Construction work
- 29,315
- median open notice
- €810,556
Who wins in this market
Many suppliersFinland · Construction work
- different companies won awards here
- 337
- of the awards went to the three most frequent winners
- 7%
- buyers awarded contracts here
- 200
Based on 519 awards with a named winner over the last 3 years. Counted by award, not by value, because lot and framework amounts are not comparable. Concentrated means the three most frequent winners took 65% or more of the awards; many suppliers, under 35% with at least ten different winners.
Competition
- tenders per lot on average (open and restricted procedures)
- 5.5
- of those lots received a single tender
- 5%
- of the awards went to companies based in another country
- 1%
As the official award notices state them, over the last 3 years. Tenders per lot count open and restricted procedures only: in a negotiated procedure or a direct award a single tender is the procedure itself. The country is the one the notice gives for the winner.
Similar tenders
Open now
Awarded before
Never miss a tender like this