Awarded to
D & G DYNAMIC MAINTENANCE GROUP S.R.L.; GENERAL TURBO
- Awarded value
- €434,438 40% under the estimate of the same lots
- Bids received
- 7 over 2 lots
- Record with this buyer
- 1 first contract from this buyer in the register
Summary
Machine-generated summaryElectrocentrale Bucuresti S.A. awarded a contract for the overhaul with disassembly of two 6 KV motors serving the feed water electric pumps (EPA) and one motor serving a gas compressor, all part of the Combined Cycle Power Plant at CTE Bucuresti Vest. The contract was won by D & G DYNAMIC MAINTENANCE GROUP S.R.L. and GENERAL TURBO for EUR 434,437.85. The awarded price is 40% below the estimated value of EUR 718,850.19. Further details are set out in the specifications book, and questions could be submitted via SICAP with an extended electronic signature.
Description
2 lots
- Lot 1
- Revizie electromotor aferent Electropompa apa alimentare– 2 motoare estimated €405,936 · 3 months
- Lot 2
- Revizie electromotor aferent compresor gaz – 1 ans estimated €301,850 · 3 months
- How tenders are scored
- Pretul ofertei: 90 percent; Termen de prestare (Tn): 10 percent
As the official notice states them.
Official source
Source: TED - Tenders Electronic Daily (Publications Office of the EU)
Always verify details on the official notice.
Report an error in this notice
Last verified against TED - Tenders Electronic Daily (Publications Office of the EU) 3 days ago
What this buyer has paid before
Based on 6 comparable contracts this buyer awarded in this sector over the last 4 years.
- This award
- €434,438
- Estimated value
- €718,850
- Median award
- €615,057
- Middle half of past awards
- €412,837 to €1.3M
The award sits inside the usual range.
Most recent awards
- Repair and maintenance services of non-electric machinery - LN 3 - TA 3 type DKUL 50-1 - Full opening - Mechanical - CTE Progresu €795,675
- România - Servicii de reparare şi de întreţinere a boilerelor - LN 4 - Inlocuire suprafete de schimb de caldura aferente cazanului de abur nr. 3 tip TGM 84A din CTE Bucuresti Sud €5,501,809
- România - Servicii de reparare şi de întreţinere a maşinilor neelectrice - LN3 - Retubulare boiler orizontal tip BG-2250 aferent TA nr.3 - CTE Bucuresti SUD €405,637
- România - Servicii de reparare şi de întreţinere a boilerelor - LN3 Retubulare schimbator de caldura cazan recuperator de la Centrala cu Ciclu Combinat din CTE Bucuresti Vest €292,535
Award values as published by the official sources. Use them as a guide, not a rule: scope, lots and duration differ between contracts.
The buyer
Full buyer profileElectrocentrale Bucuresti S.A.
- notices in the register
- 57
- awards
- 17
- awarded in total
- €57.4M
Who wins its contracts
Moderately concentrated- different companies won its awards
- 12
- of the awards went to the three most frequent winners
- 36%
- of its calls state an estimated value
- 100%
Based on 14 awards with a named winner over the last 3 years. Counted by award, not by value, because lot and framework amounts are not comparable. Concentrated means the three most frequent winners took 65% or more of the awards; many suppliers, under 35% with at least ten different winners.
Competition
- tenders per lot on average (open and restricted procedures)
- 3.2
- of those lots received a single tender
- 21%
- of the awards went to companies based in another country
- 0%
As the official award notices state them, over the last 3 years. Tenders per lot count open and restricted procedures only: in a negotiated procedure or a direct award a single tender is the procedure itself. The country is the one the notice gives for the winner.
Awards most often to
5 open tenders right now
- Construction works for cogeneration plants - Implementation of a peak-load thermal energy production plant running on natural gas at the Progresu CHP plant 5 days left
- Construction works for cogeneration plants - Implementation of a peak-load thermal energy production plant running on natural gas at the Progresu thermal energy plant 20 days left
- Construction works for cogeneration plants - Implementation of a peak-load heat production facility running on natural gas at the Progresu thermal power plant 36 days left
Market context
- open now in Repair & maintenance services
- 4,792
- median open notice
- €268,640
Who wins in this market
Many suppliersRomania · Repair & maintenance services
- different companies won awards here
- 768
- of the awards went to the three most frequent winners
- 3%
- buyers awarded contracts here
- 312
Based on 1,780 awards with a named winner over the last 3 years. Counted by award, not by value, because lot and framework amounts are not comparable. Concentrated means the three most frequent winners took 65% or more of the awards; many suppliers, under 35% with at least ten different winners.
Competition
- tenders per lot on average (open and restricted procedures)
- 1.2
- of those lots received a single tender
- 49%
- of the awards went to companies based in another country
- 1%
- of the tenders came from another country
- 8%
As the official award notices state them, over the last 3 years. Tenders per lot count open and restricted procedures only: in a negotiated procedure or a direct award a single tender is the procedure itself. The country is the one the notice gives for the winner.
Similar tenders
Open now
Awarded before
Never miss a tender like this
47 new notices in Repair & maintenance services in Romania in the last 7 days. Get an email when new ones appear. Free.
Set up my alertOr follow just its CPV code, Repair and maintenance services of electric motors: an email when new tenders arrive under it, no account needed.