Awarded to
STRABAG AG Direktion Niedersachsen/Sachsen-Anhalt Bereich Hannover
- Award date
- Bids received
- 8 over 2 lots
- Record with this buyer
- 1 first contract from this buyer in the register
- Back on the market
- Jul 2027 How we know
When this contract comes back
This contract runs about 17 months, so it is back on the market around July 2027.
Every contract expiring, on the radarSummary
Machine-generated summaryenercity Netz GmbH awarded a contract for construction of the 'Geothermie' district heat transport pipeline in Hanover, running from Karl-Wiechert-Allee to the planned geothermal plant in Hannover-Lahe on Alte Peiner Heerstrasse. The pipeline connects the existing district heat network with the geothermal plant as a new heat feeder. The works were split into two lots covering around 2,190 m and 2,550 m of pipeline, including a new shaft structure and integration into the existing steel jacket pipe route. Crossing of the Mittellandkanal was carried out separately. STRABAG AG Direktion Niedersachsen/Sachsen-Anhalt Bereich Hannover won the contract. It was awarded on 12 November 2025, lasts 17 months and ends, returning to market, on 31 July 2027.
Description
Official source
Source: TED - Tenders Electronic Daily (Publications Office of the EU)
Always verify details on the official notice.
Report an error in this notice
Last verified against TED - Tenders Electronic Daily (Publications Office of the EU) 1 week ago
What this market pays
The buyer has too few awards of its own in this sector, so this is the range of the last 2,000 awards for Construction work in Germany.
- Median award
- €274,553
- Middle half of past awards
- €118,236 to €717,961
TED - Tenders Electronic Daily (Publications Office of the EU) publishes no value for this notice, so it has no mark on the scale. The official documents may state one.
Award values as published by the official sources. Use them as a guide, not a rule: scope, lots and duration differ between contracts.
The buyer
Full buyer profileenercity Netz GmbH
- notices in the register
- 65
- awards
- 34
- awarded in total
- €38.3M
Who wins its contracts
Many suppliers- different companies won its awards
- 21
- of the awards went to the three most frequent winners
- 22%
Based on 23 awards with a named winner over the last 3 years. Counted by award, not by value, because lot and framework amounts are not comparable. Concentrated means the three most frequent winners took 65% or more of the awards; many suppliers, under 35% with at least ten different winners.
Competition
- of the awards went to companies based in another country
- 5%
As the official award notices state them, over the last 3 years. Tenders per lot count open and restricted procedures only: in a negotiated procedure or a direct award a single tender is the procedure itself. The country is the one the notice gives for the winner.
One dot per award, on the day it was signed, sized by its value. A ring is an award with no published value.
Awards most often to
5 open tenders right now
- Pipeline and civil engineering works in the construction project HW Fössestraße 7 days left
- Construction works - Structural and civil engineering works, trough channel, Herrenhausen power plant 25 days left
- Maintenance of gas consumption installations - Inspection of low-pressure gas service connections according to DVGW G 465-1 No deadline published
Market context
- open now in Construction work
- 19,935
- median open notice
- €547,553
Who wins in this market
Many suppliersGermany · Construction work
- different companies won awards here
- 12,328
- of the awards went to the three most frequent winners
- 1%
- buyers awarded contracts here
- 2,985
Based on 27,178 awards with a named winner over the last 3 years. Counted by award, not by value, because lot and framework amounts are not comparable. Concentrated means the three most frequent winners took 65% or more of the awards; many suppliers, under 35% with at least ten different winners.
Competition
- tenders per lot on average (open and restricted procedures)
- 6.3
- of those lots received a single tender
- 7%
- of the awards went to companies based in another country
- 1%
- of the tenders came from another country
- 1%
As the official award notices state them, over the last 3 years. Tenders per lot count open and restricted procedures only: in a negotiated procedure or a direct award a single tender is the procedure itself. The country is the one the notice gives for the winner.
Similar tenders
Open now
Awarded before
Never miss a tender like this
1,841 new notices in Construction work in Germany in the last 7 days. Get an email when new ones appear. Free.
Set up my alertOr follow just its CPV code, Construction work for communication lines: an email when new tenders arrive under it, no account needed.