Awarded to
- Awarded value
- €137,915 13% under the estimate of the same lots
- Award date
- decided 101 days after the deadline
- Bids received
- 2
- Back on the market
- Dec 2026 How we know
When this contract comes back
estimated from the stated durationThis contract runs about 2 months, so it is back on the market around December 2026.
Every contract expiring, on the radarSummary
Machine-generated summaryThe Junta de Gobierno del Ayuntamiento de Vigo awarded a contract for the execution of the works of the project 'New enclosures at the Samil sports complex'. The contract was won by ZONA DE OBRA O ROSAL SL for EUR 137,914.65. The estimated value was EUR 158,159, so the awarded price was 13% below the estimate. The contract was awarded on 2 October 2026, and the deadline for bids was 22 June 2026. The procurement has been completed.
Key points
- Status at the source
- Awarded
- Reference
- 2565-441
Original text
Official source
Source: PLACSP - Plataforma de Contratación del Sector Público
Always verify details on the official notice.
Report an error in this notice
Last verified against PLACSP - Plataforma de Contratación del Sector Público 14 hours ago
What this market pays
The buyer has too few awards of its own in this sector, so this is the range of the last 2,000 awards for Construction work in Spain.
- This award
- €137,915
- Estimated value
- €158,159
- Median award
- €28,633
- Middle half of past awards
- €7,433 to €344,309
The award sits inside the usual range.
Award values as published by the official sources. Use them as a guide, not a rule: scope, lots and duration differ between contracts.
The buyer
Full buyer profileJunta de Gobierno del Ayuntamiento de Vigo
Who wins its contracts
Many suppliers- different companies won its awards
- 75
- of the awards went to the three most frequent winners
- 13%
- of its calls state an estimated value
- 99%
Based on 91 awards with a named winner over the last 3 years. Counted by award, not by value, because lot and framework amounts are not comparable. Concentrated means the three most frequent winners took 65% or more of the awards; many suppliers, under 35% with at least ten different winners.
Competition
- tenders per lot on average (open and restricted procedures)
- 2.7
- of those lots received a single tender
- 31%
- of the awards went to companies based in another country
- 0%
As the official award notices state them, over the last 3 years. Tenders per lot count open and restricted procedures only: in a negotiated procedure or a direct award a single tender is the procedure itself. The country is the one the notice gives for the winner.
Recent awards
- Selective collection, transport and valorisation of plant waste produced by care, conservation and maintenance work in the green areas of Castro park, and in newly created green areas before they can be included in the concessionary company's maintenance
- O desenvolvemento da exposición temporal "Jules Verne 200"
- O alugueiro, instalación e mantemento dun sistema de megafonía no ámbito da programación do Nadal (2026-2027 e 2027-2028)
7 open tenders right now
- Construction of a retaining wall and fencing at the CEIP Mestres Goldar primary school on the Costa street frontage (Castrelos) 5 days left
- Provision of catering services for institutional receptions, official events, working meetings, protocol events and other activities organised by the City Council of Vigo 5 days left
- Construction works for the dog leisure area in the Barreiro green zone of the municipality of Vigo 11 days left
Market context
- open now in Construction work
- 29,461
- median open notice
- €808,210
Who wins in this market
Many suppliersSpain · Construction work
- different companies won awards here
- 10,340
- of the awards went to the three most frequent winners
- 2%
- winners of the last 12 months were new here
- 10,009 of 10,157
- buyers awarded contracts here
- 4,463
Based on 21,445 awards with a named winner over the last 3 years. Counted by award, not by value, because lot and framework amounts are not comparable. Concentrated means the three most frequent winners took 65% or more of the awards; many suppliers, under 35% with at least ten different winners. New: no award from the same buyer or market in the two years before.
Competition
- tenders per lot on average (open and restricted procedures)
- 7.4
- of those lots received a single tender
- 21%
- of the awards went to companies based in another country
- 1%
- of the tenders came from another country
- 5%
As the official award notices state them, over the last 3 years. Tenders per lot count open and restricted procedures only: in a negotiated procedure or a direct award a single tender is the procedure itself. The country is the one the notice gives for the winner.
Change history
Every time an official source republished this notice with different content. We watch every source we index, including regional copies of the same notice.
-
- Status
-
Was:
Closed - Now: Awarded
- Award date
- not stated
- Now: October 1, 2026
- Scope and criteria
- The description was expanded. Re-read it before you bid.
- Winner
- not stated
- Now: ZONA DE OBRA O ROSAL SL
- Award value
- not stated
- Now: €137,915
-
- Title
-
Was:
A execución das obras do proxecto de “Novos peches no complexo polideportivo de... - Now: A execución das obras do proxecto de "Novos peches no complexo polideportivo de...
- Scope and criteria
- The description was shortened. Re-read it before you bid.
-
- Scope and criteria
- The description was expanded. Re-read it before you bid.
-
- Scope and criteria
- The description was shortened. Re-read it before you bid.
Follow this tender and we email you the moment it changes. Create account
Similar tenders
Open now
4
days left
€396,636
est. value
5
days left
€141,513
est. value
4
days left
€55,263
est. value
5
days left
€218,027
est. value
Awarded before
Never miss a tender like this
2,105 new notices in Construction work in Spain in the last 7 days. Get an email when new ones appear. Free.