Rehabilitación del polígono empresarial Lysons Enterprise Estate
Órgano de contratación: Guildford Borough Council
País: Reino Unido
Procedimiento: Otro procedimiento
Sector (CPV): Trabajos de construcción (45112700)
Aperlena: https://aperlena.com/es/t/refurbishment-of-lysons-enterprise-estate-0a888b23fd
Anuncio oficial: https://www.find-tender.service.gov.uk/Notice/092174-2026
Te escribimos si cambia el plazo o se publica una corrección. Gratis.
Iniciar sesión
01
Resumen
Resumen generado automáticamente
El Guildford Borough Council solicita manifestaciones de interés de contratistas de diseño y construcción para la rehabilitación del polígono empresarial Lysons Enterprise Estate, naves industriales ligeras construidas en los años ochenta en Guildford que requieren importantes obras de modernización. Las obras afectan a 15 unidades autónomas distribuidas en tres hileras, de estructura de acero con chapas perfiladas, con unos 1.148 m2 de superficie bruta interior en una parcela de 4.611 m2. Las unidades no cumplen actualmente los estándares mínimos de eficiencia energética (MEES); el ayuntamiento busca adecuarlas a las necesidades de los ocupantes, cumplir la normativa MEES y alcanzar una calificación energética EPC 'A'. La contratación sigue una vía de diseño y construcción en dos fases: una fase 1 mediante un acuerdo de servicios de preconstrucción y una fase 2 con contrato de diseño y construcción en el que el contratista completa el diseño y ejecuta las obras.
02
Descripción
Guildford Borough Council are seeking expression of interest from D&B Contractors for the refurbishment of 19 light industrial units constructed in the 1980’s which have now reached the end of their useful life and require significant upgrading works. The Council intends to follow a 2-stage Design & Build procurement route comprising a Stage 1 PCSA followed by a Stage 2 Design & Build Contract The contractor will be required to assume responsibility for completion of the design and delivery of the works under a Design & Build contract.
Arranged in three terraces, to provide individual self-contained units, the construction is steel frame with powder coated, profiled steel sheeting and incorporating glazed panels. Each unit has an up and over loading door (manually operated) along with personnel door. Internally the units are single storey and open plan except for a WC block. Electricity and gas are connected. The eaves height is approx. 3.2 m. The units were originally built with lighting but no heating, though over the years some tenants have installed heating and internal fit outs to varying degrees. Externally there is parking, circulation areas and landscaping.
Floor areas: Buildings: 1,155 sq m GIA (Combined units)
Total Site area: 4,611 sq m (1.14 acres).
The units are currently failing the Minimum Energy Efficiency Standards (MEES) regulations.
The Council is now undertaking a programme of refurbishment to upgrade the existing accommodation to a standard that meets occupier requirements, ensuring compliance with MEES regulation, whilst seeking to achieve an EPC rating of ‘A’ across the estate.
Scope of works:
Unit mix:
• 8 single bay (mid terrace) 56 sqm
• 3 single bay (end terrace) 59 sqm
• 3 twin bay 117 sqm
• 1 triple bay 172 sqm
Total number of units:15
Total gross internal area: 1,148 sqm (all ground floor as per existing).
The appointment is expected to be split into a 2 stage tender:
Stage 1: Appointment under a Pre-Construction Services Agreement (PCSA) to develop the design, support planning, undertake surveys, develop the contractor's proposals, programme and target cost/open book pricing. This is to include but is not limited to:
• Develop designs and submit planning application
• Review buildability
• Undertake surveys
• Develop construction methodology
• Review phasing and tenant impacts
• Develop programme
• Develop package procurement strategy
• Produce open-book pricing
• Identify risks and value engineering opportunities
Stage 2: Subject to successful completion of Stage 1, approval of the developed design, agreed contract sum and governance approvals, the Council may enter into a Design & Build Contract with the Stage 1 contractor to deliver the works.
The construction works are likely to include:
• Recladding of the three existing terraces including associated work to mechanical and electrical services, if required, and repairs to external works.
• New doors and windows
• PV panels to upgrade to EPC A only as required
• Limited landscaping works and tree works
• No new service connections
• No significant external works other than making good and repair
Draft Timescales:
Soft market engagement: October 2026
Executive Approval: October 2026
ITT for PCSA Stage 1: October- December 2026
PCSA Stage 1: Contract Award: January 2027
RIBA 1-3 (until planning submission): February - March 2027
Stage 2 Contract Negotiation, Governance and Award: April - September 2027
Construction: January 2028 - December 2028
Fuente oficial
Fuente: Find a Tender Service (UK Cabinet Office / Crown Commercial Service)
Verifica siempre los detalles en el anuncio oficial.
de las adjudicaciones fueron a los tres adjudicatarios más frecuentes
6%
compradores adjudicaron contratos aquí
363
Según 1.292 adjudicaciones con adjudicatario identificado en los últimos 3 años. Contadas por adjudicación y no por importe, porque los importes de lotes y acuerdos marco no son comparables.
Concentrado: los tres adjudicatarios más frecuentes obtuvieron el 65% de las adjudicaciones o más; muchos proveedores: menos del 35% con al menos diez adjudicatarios distintos.